All of our projects

under-construction

Aix-en-Provence (Aix-Marseille-Provence Métropole)

Under construction

France

WAGABOX® Model

1000 scfm

Commissioning

March 2027

Installed capacity

187,668 MMBtu/year

Distance to pipeline

0.7 miles

Landfill gas composition

CH4

-

N2

-

under-construction

City of Beaumont Landfill (Beaumont, TX)

Under construction

United States

WAGABOX® Model

2000 scfm

Commissioning

2026

Installed capacity

406,045 MMBtu/year

Distance to pipeline

0.05 miles

Landfill gas composition

CH4

-

N2

-

under-construction

Bena Landfill (Bakersfield, CA)

Under construction

United States

WAGABOX® Model

3000 scfm

Commissioning

Q1-2027

Installed capacity

545,943 MMBtu/year

Distance to pipeline

2.2 miles

Landfill gas composition

CH4

-

N2

-

Image-WB-Blaringhem-720x324

Blaringhem (Baudelet)

Operational

France

WAGABOX® Model

375 scfm

Commissioning

September 2020

Installed capacity

85,304 MMBtu/year

Distance to pipeline

0.4 miles

Landfill gas composition

CH4

39,30%

N2

26,60%

Can Mata (PreZero)

Operational

Spain

WAGABOX® Model

1500 scfm

Commissioning

June 2023

Installed capacity

272,971 MMBtu/year

Distance to pipeline

2.5 miles

Landfill gas composition

CH4

47,10%

N2

18,00%