Our projects
Discover our projects
around the world
WAGABOX® units are deployed worldwide through long-term partnerships with landfills and local authorities. New renewable natural gas projects from waste are under development across Europe and North America, helping make renewable gas accessible to more people
95%
WAGABOX® facility availability
57
WAGABOX® units worldwide
19 under construction and 38 operational
504k
tons of
of CO₂ equivalent emissions avoided since 2015
7.98 M
MMBtu of
RNG injected since 2015
All of our projects

CMCMUA Secure Sanitary Landfill (Woodbine, NJ)
Under construction
United States
WAGABOX® Model
1000 scfm
Commissioning
Q1-2028
Installed capacity
204,729 MMBtu/year
Distance to pipeline
1 mile
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Chatuzange-le-Goubet (Veolia)
Operational
France
WAGABOX® Model
375 scfm
Commissioning
November 2024
Installed capacity
85,304 MMBtu/year
Distance to pipeline
3.2 miles
Landfill gas composition
CH4
44,50%
N2
17,60%

Site operator
Utility
Gas offtaker

Chemung Landfill (Elmira, NY)
Operational
United States
WAGABOX® Model
3000 scfm
Commissioning
Q3-2025
Installed capacity
610,773 MMBtu/year
Distance to pipeline
4.5 miles
Landfill gas composition
CH4
44,70%
N2
19,60%

Site operator
Utility
Gas offtaker

Chevilly (Suez)
Operational
France
WAGABOX® Model
250 scfm
Commissioning
December 2018
Installed capacity
51,182 MMBtu/year
Distance to pipeline
3.7 miles
Landfill gas composition
CH4
44,30%
N2
20,90%

Site operator
Utility
Gas offtaker

Inzinzac-Lochrist (Lorient Agg)
Operational
France
WAGABOX® Model
250 scfm
Commissioning
November 2019
Installed capacity
51,182 MMBtu/year
Distance to pipeline
3.7 miles
Landfill gas composition
CH4
46,90%
N2
13,80%

Site operator
Utility