Our projects
Discover our projects
around the world
WAGABOX® units are deployed worldwide through long-term partnerships with landfills and local authorities. New renewable natural gas projects from waste are under development across Europe and North America, helping make renewable gas accessible to more people
95%
WAGABOX® facility availability
57
WAGABOX® units worldwide
19 under construction and 38 operational
504k
tons of
of CO₂ equivalent emissions avoided since 2015
7.98 M
MMBtu of
RNG injected since 2015
All of our projects

Chicoutimi (Matrec-GFL)
Operational
Canada
WAGABOX® Model
375 scfm
Commissioning
December 2023
Installed capacity
85,304 MMBtu/year
Distance to pipeline
0.6 miles
Landfill gas composition
CH4
46,90%
N2
19,60%

Site operator
Utility
Gas offtaker

Claye-Souilly (Veolia)
Operational
France
WAGABOX® Model
2000 scfm
Commissioning
March 2022
Installed capacity
409,457 MMBtu/year
Distance to pipeline
13.5 miles
Landfill gas composition
CH4
41,40%
N2
20,30%

Site operator
Utility

Gas offtaker

Clermont-Ferrand (Valtom)
Operational
France
WAGABOX® Model
250 scfm
Commissioning
December 2024
Installed capacity
51,182 MMBtu/year
Distance to pipeline
0.4 miles
Landfill gas composition
CH4
47,40%
N2
13,00%

Site operator
Utility
Gas offtaker

Cowansville (Régie de Brome-Missisquoi)
Operational
Canada
WAGABOX® Model
750 scfm
Commissioning
July 2024
Installed capacity
102,364 MMBtu/year
Distance to pipeline
3.1 miles
Landfill gas composition
CH4
41,70%
N2
25,30%

Site operator
Utility
Gas offtaker

CTR Cogersa (Cogersa)
Under construction
Spain
WAGABOX® Model
1000 scfm
Commissioning
May 2028
Installed capacity
204,729 MMBtu/year
Distance to pipeline
0.6 miles
Landfill gas composition
CH4
-
N2
-