Our projects

Discover our projects
around the world

WAGABOX® units are deployed worldwide through long-term partnerships with landfills and local authorities. New renewable natural gas projects from waste are under development across Europe and North America, helping make renewable gas accessible to more people

95%

WAGABOX® facility availability

57

WAGABOX® units worldwide

19 under construction and 38 operational

504k

tons of

of CO₂ equivalent emissions avoided since 2015

7.98 M

MMBtu of

RNG injected since 2015

All of our projects

under-construction

Miramundo (Bioreciclaje de Cadiz)

Under construction

Spain

WAGABOX® Model

1500 scfm

Commissioning

October 2026

Installed capacity

272,971 MMBtu/year

Distance to pipeline

5.6 miles

Landfill gas composition

CH4

-

N2

-

Monflanquin (Valorizon et Avergies)

Monflanquin (Valorizon et Avergies)

Operational

France

WAGABOX® Model

250 scfm

Commissioning

January 2026

Installed capacity

40,946 MMBtu/year

Distance to pipeline

0.2 miles

Landfill gas composition

CH4

44,80%

N2

17,90%

Montois

Montois-la-Montagne (Suez)

Operational

France

WAGABOX® Model

250 scfm

Commissioning

January 2023

Installed capacity

85,304 MMBtu/year

Distance to pipeline

2.8 miles

Landfill gas composition

CH4

40,70%

N2

24,80%

Waga_Bath00027-43-720x480

Bath Landfill (Steuben County, NY)

Operational

United States

WAGABOX® Model

1000 scfm

Commissioning

March 2024

Installed capacity

204,729 MMBtu/year

Distance to pipeline

2.8 miles

Landfill gas composition

CH4

44,20%

N2

23,30%

under-construction

Newland Park Landfill (Salisbury, MD)

Under construction

United States

WAGABOX® Model

1000 scfm

Commissioning

Installed capacity

211,553 MMBtu/year

Distance to pipeline

4 miles

Landfill gas composition

CH4

-

N2

-

Discover our WAGABOX® technology