Our projects

Discover our projects
around the world

WAGABOX® units operate globally via long-term partnerships with landfills and authorities, with multiple projects aiming to make biomethane widely accessible

95%

WAGABOX® facility availability

57

WAGABOX® units worldwide

19 under construction and 38 operational

504k

tons of

of CO₂ equivalent emissions avoided since 2015

2,338

GWh of

biomethane injected since 2015

All of our projects

under-construction

Hay Road (G2)

Under construction

United States

WAGABOX® Model

4800 m3/h

Commissioning

2026

Installed capacity

123 GWh/year

Distance to pipeline

1,61 km

Landfill gas composition

CH4

-

N2

-

Wagabox Pavie (Trigone)

Pavie (Trigone)

Operational

France

WAGABOX® Model

400 m3/h

Commissioning

May 2018

Installed capacity

15 GWh/year

Distance to pipeline

3 km

Landfill gas composition

CH4

47,50%

N2

14,20%

under-construction

Podere Rota (CSAI)

Under construction

Italy

WAGABOX® Model

400 m3/h

Commissioning

September 2026

Installed capacity

29 GWh/year

Distance to pipeline

0,58 km

Landfill gas composition

CH4

-

N2

-

under-construction

Polo Industriale Scapigliato (Scapigliato)

Under construction

Italy

WAGABOX® Model

2400 m3/h

Commissioning

December 2026

Installed capacity

92 GWh/year

Distance to pipeline

2,3 km

Landfill gas composition

CH4

-

N2

-

under-construction

Rockingham (Rockingham County)

Under construction

United States

WAGABOX® Model

1600 m3/h

Commissioning

2026

Installed capacity

60 GWh/year

Distance to pipeline

3,22 km

Landfill gas composition

CH4

-

N2

-