Our projects
Discover our projects
around the world
WAGABOX® units operate globally via long-term partnerships with landfills and authorities, with multiple projects aiming to make biomethane widely accessible
95%
WAGABOX® facility availability
57
WAGABOX® units worldwide
19 under construction and 38 operational
504k
tons of
of CO₂ equivalent emissions avoided since 2015
2,338
GWh of
biomethane injected since 2015
All of our projects

Cape May (CMCMUA)
Under construction
United States
WAGABOX® Model
1600 m3/h
Commissioning
Q1-2028
Installed capacity
60 GWh/year
Distance to pipeline
1,61 km
Landfill gas composition
CH4
-
N2
-

Site operator
Utility
Gas offtaker

Chatuzange-le-Goubet (Veolia)
Operational
France
WAGABOX® Model
400 m3/h
Commissioning
November 2024
Installed capacity
25 GWh/year
Distance to pipeline
5,1 km
Landfill gas composition
CH4
44,50%
N2
17,60%

Site operator

Utility
Gas offtaker

Chemung (Casella)
Operational
United States
WAGABOX® Model
4800 m3/h
Commissioning
Q3-2025
Installed capacity
179 GWh/year
Distance to pipeline
7,24 km
Landfill gas composition
CH4
44,70%
N2
19,60%

Site operator
Utility
Gas offtaker

Chevilly (Suez)
Operational
France
WAGABOX® Model
400 m3/h
Commissioning
December 2018
Installed capacity
15 GWh/year
Distance to pipeline
6 km
Landfill gas composition
CH4
44,30%
N2
20,90%

Site operator

Utility
Gas offtaker

Chicoutimi (Matrec-GFL)
Operational
Canada
WAGABOX® Model
400 m3/h
Commissioning
December 2023
Installed capacity
25 GWh/year
Distance to pipeline
1 km
Landfill gas composition
CH4
46,90%
N2
19,60%

Site operator