Our projects

Discover our projects
around the world

WAGABOX® units operate globally via long-term partnerships with landfills and authorities, with multiple projects aiming to make biomethane widely accessible

95%

Industrial units availability

5

WAGABOX® units in Canada

4 operational and 1 under construction

504k

tons

of CO₂ equivalent emissions avoided since 2015

8.42 M

GJ of

RNG injected since 2015

All of our projects

under-construction

Polo Industriale Scapigliato (Scapigliato)

Under construction

Italy

WAGABOX® Model

1500 scfm

Commissioning

December 2026

Installed capacity

331 200 GJ/year

Distance to pipeline

2,3 km

Landfill gas composition

CH4

-

N2

-

under-construction

Rockingham (Rockingham County)

Under construction

United States

WAGABOX® Model

1000 scfm

Commissioning

2026

Installed capacity

216 000 GJ/year

Distance to pipeline

3,22 km

Landfill gas composition

CH4

-

N2

-

Saint-Etienne-des-Grès (Enercycle)

Operational

Canada

WAGABOX® Model

2000 scfm

Commissioning

May 2023

Installed capacity

468 000 GJ/year

Distance to pipeline

N/A

Landfill gas composition

CH4

46,60%

N2

19,80%

Saint-Florentin (Coved – Paprec)

Operational

France

WAGABOX® Model

375 scfm

Commissioning

February 2017

Installed capacity

90 000 GJ/year

Distance to pipeline

3 km

Landfill gas composition

CH4

45,50%

N2

20,00%

saint-gaudens

Saint-Gaudens (Sivom SGMAM)

Operational

France

WAGABOX® Model

500 scfm

Commissioning

January 2020

Installed capacity

126 000 GJ/year

Distance to pipeline

7,2 km

Landfill gas composition

CH4

41,80%

N2

27,10%