Our projects

WAGABOX® units are deployed worldwide through long-term partnerships with landfills and local authorities. Numerous projects to produce renewable natural gas from waste are under development in Europe and North America, with the shared goal of making renewable gas accessible to as many people as possible.

 

Visit a WAGABOX® unit

The first WAGABOX® commissioned in the United-States

WAGABOX® unit of Bath (United States)
Commissioning
15 March 2024
Installed capacity
207,000 mmBtu/year
Site operator
Logo Steuben
Utility
Logo Corning
All of our projects
Operational
WAGABOX® unit of Gournay
Commissioning
January 2022
Installed capacity
51,180 mmBtu/year
Site operator
Logo SEG
Utility
Logo GRDF
Gas offtaker
Logo SEG
Type of site
85,000 tons
Waste stored/year
8 miles
Distance to pipeline
Landfill gas composition

45-50%

CH4

0-3%

O2

600 ppmv

H2S

15-20%

N2

Operational
WAGABOX® unit of Blaringhem (Baudelet)
Commissioning
September 2020
Installed capacity
85,300 mmBtu/year
Site operator
Logo Baudelet
Utility
Logo GRDF
Gas offtaker
Logo Baudelet
Type of site
200,000 tons
Waste stored/year
0.4 miles
Distance to pipeline
Landfill gas composition

40-50%

CH4

0-3%

O2

300 ppmv

H2S

5-20%

N2

Operational
WAGABOX® unit of St-Gaudens (Liéoux)
Commissioning
January 2020
Installed capacity
119,400 mmBtu/year
Site operator
Logo Sivom
Utility
Logo GRDF
Gas offtaker
Logo Provirdis
Type of site
85,000 tons
Waste stored/year
4.3 miles
Distance to pipeline
Landfill gas composition

40-45%

CH4

0-3%

O2

500 ppmv

H2S

5-20%

N2

Co-funded by
Logo Meridiam
Operational
WAGABOX® unit of Les Ventes-de-Bourse
Commissioning
January 2020
Installed capacity
85,300 mmBtu/year
Site operator
Logo Suez
Utility
Logo GRDF
Gas offtaker
Logo Suez
Type of site
120,000 tons
Waste stored/year
8.6 miles
Distance to pipeline
Landfill gas composition

40-45%

CH4

0-3%

O2

4000 ppmv

H2S

10-20%

N2

Operational
WAGABOX® unit of Inzinzac-Lochrist (Kermat)
Commissioning
November 2019
Installed capacity
51,180 mmBtu/year
Site operator
Lorient Agglomeration Logo
Utility
Logo GRDF
Gas offtaker
Logo Dalkia
Type of site
60,000 tons
Waste stored/year
3.7 miles
Distance to pipeline
Landfill gas composition

45-50%

CH4

0-3%

O2

4000 ppmv

H2S

5-20%

N2

Operational
WAGABOX® unit of Chevilly
Commissioning
December 2018
Installed capacity
54,180 mmBtu/year
Site operator
Logo Suez
Utility
Logo GRDF
Gas offtaker
Logo Suez
Type of site
60,000 tons
Waste stored/year
3.7 miles
Distance to pipeline
Landfill gas composition

45-50%

CH4

0-3%

O2

4000 ppmv

H2S

5-20%

N2

Operational
WAGABOX® unit of Gueltas
Commissioning
November 2018
Installed capacity
85,300 mmBtu/year
Site operator
Logo Suez
Utility
Logo GRDF
Gas offtaker
Logo Suez
Type of site
200,000 tons
Waste stored/year
3.7 miles
Distance to pipeline
Landfill gas composition

45-50%

CH4

3.5%

O2

1000 ppmv

H2S

5-20%

N2

Operational
WAGABOX® unit of Saint-Palais
Commissioning
November 2018
Installed capacity
68,200 mmBtu/year
Site operator
Logo Veolia PROJET
Utility
Logo GRDF
Gas offtaker
Logo Dalkia
Type of site
90,000 tons
Waste stored/year
0.6 miles
Distance to pipeline
Landfill gas composition

40-50%

CH4

O-3%

O2

1000 ppmv

H2S

5-20%

N2

Operational
WAGABOX® unit of Pavie
Commissioning
May 2018
Installed capacity
51,180 mmBtu/year
Site operator
Logo Trigone
Utility
Logo GRDF
Gas offtaker
Air Liquide logo
Type of site
40,000 tons
Waste stored/year
1.8 miles
Distance to pipeline
Landfill gas composition

45%

CH4

0-3%

O2

500 ppmv

H2S

5-25%

N2

Operational
WAGABOX® unit of Saint-Maximin
Commissioning
June 2017
Installed capacity
85,300 mmBtu/year
Site operator
Logo Suez
Utility
Logo GRDF
Gas offtaker
Logo Suez
Type of site
200,000 tons
Waste stored/year
0.7 miles
Distance to pipeline
Landfill gas composition

45-50%

CH4

0-3%

O2

7000 ppmv

H2S

5-20%

N2

Operational
WAGABOX® unit of Saint-Florentin
Commissioning
February 2017
Installed capacity
85,300 mmBtu/year
Site operator
Logo Paprec
Utility
Logo GRDF
Gas offtaker
Air Liquide logo
Type of site
70,000 tons
Waste stored/year
1.8 miles
Distance to pipeline
Landfill gas composition

40-50%

CH4

0-3%

O2

1500

H2S

5-25%

N2

Under construction
WAGABOX® unit of Clermont-Ferrand (Puy-Long)
Commissioning
2024
Installed capacity
426,517 mmBtu/year
Site operator
Logo Valtom
Under construction
WAGABOX® unit in Pennsylvania State
Commissioning
2023
Installed capacity
450,000 mmBtu/year
Site operator
Logo Pennsylvania States
Under construction
WAGABOX® unit of Hartland (Canada)
Commissioning
2024
Installed capacity
341,214 mmBtu/year
Site operator
Logo CRD