Once the contract has been signed, commissioning typically takes place within 18 to 24 months. This timeframe covers the manufacturing of the WAGABOX® unit in our workshops, the obtaining of regulatory permits, civil engineering works, and connection to the gas grid. Waga Energy coordinates all of these stages and supports you through to the injection of the first cubic meters of biomethane into the network.