Fifteen WAGABOX® units in operation

Waga Energy operates fifteen WAGABOX® units and has contracts with major waste management companies, as well as with local authorities. Fifteen more units are under construction, in the USA, Canada, France and Spain.

Saint-Florentin

Capacity: 85,300 mmBtu/year

Landfill operator: Coved Environnement
Commissioning: February 14, 2017
Distance of the gas grid: 1.8 miles

Saint-Maximin

Capacity: 85,300 mmBtu/year

Landfill operator: Suez
Commissioning: June 26, 2017
Distance of the gas grid: 0.7 miles

Pavie

Capacity: 51,180 mmBtu/year

Landfill operator: Trigone
Commissioning: May 30, 2018
Distance of the gas grid: 1.8 miles

Saint-Palais

Capacity: 68,200 mmBtu/year

Landfill operator: Veolia
Commissioning: November 6, 2018
Distance of the gas grid: 0.6 miles

Gueltas

Capacity: 85,300 mmBtu/year

Landfill operator: Suez
Commissioning: November 13, 2018
Distance of the gas grid: 3.7 miles

Chevilly

Capacity: 51,180 mmBtu/year

Landfill operator: Suez
Commissioning: December 20, 2018
Distance of the gas grid: 3.7 miles

Izinzac-Lochrist

Capacity: 51,180 mmBtu/year

Landfill operator: Lorient Agglomération
Commissioning: November 26, 2019
Distance of the gas grid: 3.7 miles

Les-Ventes-de-Bourse

Capacity: 85,300 mmBtu/year

Landfill operator: Suez
Commissioning: January 15, 2020
Distance of the gas grid: 8.6 miles

Liéoux

Capacity: 119,400 mmBtu/year

Landfill operator: Sivom SGMAM
Commissioning: January 16, 2020
Distance of the gas grid: 4.3 miles

Le Ham

Capacity: 68,200 mmBtu/year

Landfill operator: Veolia
Commissioning: April 11, 2022
Distance of the gas grid: 6.7 miles

Blaringhem

Capacity: 85,300 mmBtu/year

Landfill operator: Baudelet Environnement
Commissioning: September 2, 2020
Distance of the gas grid: 0.7 miles

Gournay

Capacity: 51,180 mmBtu/year

Landfill operator: SEG
Commissioning: January 26, 2022
Distance of the gas grid: 13 miles

Claye-Souilly

Capacity: 409,000 mmBtu/year

Landfill operator: Veolia
Commissioning: March 9, 2022
Distance of the gas grid: 21.8 miles

Chatuzange-le-Goubet

Capacity: 61,410 mmBtu/year

Landfill operator: Veolia
Commissioning: 2024

Milhac-d'Auberoche

Capacity: 68,240 mmBtu/year

Landfill operator: Suez
Commissioning: Novemnber 11,2022
Distance of the gas grid: 18 miles

Montois-la-Montagne

Capacity: 51,180 mmBtu/year

Landfill operator: Suez
Commissioning: January 26, 2023
Distance of the gas grid: 2.7 miles

Cusset

Capacity: 51,180 mmBtu/year

Landfill operator: Suez / Vichy Communauté
Commissioning: 2023

 

Sainte-Marie-Kerque

Capacity: 71,650 mmBtu/year

Landfill operator: Séché Environnement
Commissioning: 2023

Granges

Capacity: 85,300 mmBtu/year

Landfill operator: Veolia
Commissioning: 2024

Can Mata

Capacity: 238,850 mmBtu/year

Landfill operator: PreZero
Commissioning: 2023

Saint-Etienne-des-Grès

Capacity: 444,000 mmBtu/year

Landfill operator: Régie de la Mauricie
Commissioning: 2023

Cowansville

Capacity: 102,000 mmBtu/year

Landfill operator: Régie de Brome-Missisquoi
Commissioning: 2023

Hartland

Capacity: 345,000 mmBtu/year

Landfill operator: CRD
Commissioning: 2024

Bath

Capacity: 205,000 mmBtu/year

Landfill operator: Steuben County
Commissioning: 2023

Mallard Ridge

Commissioning: March 28, 2022
Landfill operator: Air Liquide

Winnebago

Landfill operator: Air Liquide
Commissioning: Early 2023 

WAGABOX® unit of Bath, NY

Landfill operator: Steuben County
Under construction
Capacity: 205,000 mmBtu/year

Delavan, WI

Landfill operator: Air Liquide
Commissioning: 28/02/2022

Winnebago, IL 

Landfill operator: Air Liquide
Under construction

WAGABOX® unit of Saint-Étienne-des-Grès, Québec

Landfill operator: Enercycle
Under construction
Capacity: 444,000 mmBtu/year

WAGABOX® unit of Cowansville,
Québec

Landfill operator: RIGMRBM
Under construction
Capacity: 102,000 mmBtu/year

WAGABOX® unit of Hartland,
British Colombia 

Landfill operator: CRD
Under construction
Capacity: 345,000 mmBtu/year

WAGABOX® unit of Saint-Florentin

Saint-Florentin landfill (France)
Commissioning: February 14, 2017

  • 70,000 tons of waste per year
  • Biogas: 40-50% CH4 | 0-3% O2 | 1,500 ppmv H2S | 5-25% N2
  • Distance of the gas grid: 1,8 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 85,300 mmBtu

WAGABOX® unit of Saint-Maximin

Saint-Maximin landfill (France)
Commissioning: June 26, 2017

  • 200,000 tons of waste per year
  • Biogas: 45-50% CH4 | 0-3% O2 | 7,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 0.7 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 85,300 mmBtu

WAGABOX® unit of Pavie

Pavie landfill (France)
Commissioning: May 30, 2018

  • 40,000 tons of waste per year
  • Biogas: 40-50% CH4 | 0-3% O2 | 500 ppmv H2S | 5-25% N2
  • Distance of the gas grid: 1.8 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 51,180 mmBtu

WAGABOX® unit of Saint-Palais

Saint-Palais lanfill (France)
Commissioning: November 6, 2018

  • 90,000 tons of waste per year
  • Biogas :40-50% CH4 | 0-3% O2 | 1,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 0.6 miles
  • Existing gas recovery solution: Combine Heat and Power
  • Capacity: 68,200 mmBtu

WAGABOX® unit of Gueltas

Gueltas landfill (France)
Commissioning: November 13, 2018

  • 200,000 tons of waste per year
  • Biogas :45-50% CH4 | 0-5% O2 | 1,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 3.7 miles
  • Existing gas recovery solution: Combine Heat and Power
  • Capacity: 85,300 mmBtu

WAGABOX® unit of Chevilly

Chevilly landfill (France)
Commissioning: December 20, 2018

  • 60,000 tons of waste per year
  • Biogas :40-50% CH4 | 0-3% O2 | 4,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 3.7 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 51,180 mmBtu

WAGABOX® unit of Izinzac-Lochrist

Izinzac-Lochrist landfill (France)
Commissioning: November 26, 2019

  • 60,000 tons of waste per year
  • Biogas: 45-50% CH4 | 0-3% O2 | 4,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 3.7 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 51,180 mmBtu
Logo Lorient Agglo

WAGABOX® unit of Les Ventes-de-Bourse

Les Ventes-de-Bourse landfill (France)
Commissioning: January 15, 2020

  • 120,000 tons of waste per year
  • Biogas: 45-50% CH4 | 0-3% O2 | 4,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 8.6 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 85,300 mmBtu
Logo Lorient Agglo
WB8

WAGABOX® unit of Liéoux

Liéoux landfill (France)
Commissioning: January 16, 2020

  • 85,000 tons of waste per year
  • Biogas: 45-50% CH4 | 0-3% O2 | 4,000 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 4.3 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 119,400 mmBtu
Logo Sivom Saint Gaudens
WB9

WAGABOX® unit of Blaringhem

Blaringhem landfill (France)
Commissioning: September 2, 2020

  • 600,000 tons of waste per year
  • Biogas: 40-50% CH4 | 0-3% O2 | 300 ppmv H2S | 5-20% N2
  • Distance of the gas grid: 0.4 miles
  • Existing gas recovery solution: four engines
  • Capacity: 85,300 mmBtu
Logo Sivom Saint Gaudens
WB11_Baudelet_Blaringhem

WAGABOX® unit of Gournay

Gournay landfill (France)
Commissioning: January 26, 2022

  • 85,000 tons of waste per year
  • Biogas: 45-50% CH4 | 0-3% O2 | 600 ppmv H2S | 15-20% N2
  • Distance of the gas grid: 8 miles
  • Existing gas recovery solution: leachate evaporation
  • Capacity: 51,180 mmBtu
Logo Sivom Saint Gaudens
WB11_Baudelet_Blaringhem

WAGABOX® unit of Claye-Souilly

Claye-Souilly landfill (France)
Commissioning: March 9, 2022

  • 1,100,000 tons of waste per year
  • Biogas: 40-50% CH4 | 0.1-3% O2 | 0-50 ppmv H2S | 1-20% N2
  • Distance of the gas grid: 13.5 miles
  • Existing gas recovery solution: Combine Heat and Power
  • Capacity: 409,000 mmBtu
Veolia
WB13

WAGABOX® unit of Milhac-d’Auberoche

Milhac-d’Auberoche landfill (France)
Commissioning: November 11, 2022

  • 105,000 tons of waste per year
  • Biogas: 40-50% CH4 | 0-3% O2 | 0-50 ppmv H2S | 1-20% N2
  • Distance of the gas grid: 11 miles
  • Capacity: 85,300 mmBtu
Logo Lorient Agglo
WB10

WAGABOX® unit of Montois-la-Montagne

Montois-la-Montagne landfill (France)
Commissioning: January 26, 2023

  • 100,000 tons of waste per year
  • Distance of the gas grid: 2.7miles
  • Capacity: 51,180 mmBtu
Logo Lorient Agglo
WB10